Bathroom Renovation Cost in Noida and Gurugram: 2026 Guide
Checked: 1 official source citedreviewed Report an error

Contents
Bathrooms are usually the first room NCR flat owners want to redo, and the hardest to estimate. A builder-finish bathroom in a 10-year-old Noida or Gurugram tower often has tired tiles, a leaking concealed pipe or a seepage patch on the ceiling of the flat below, and every contractor quotes a different number. This guide breaks a bathroom renovation into its parts, gives realistic cost ranges for each with the basis for the figure, and explains waterproofing, plumbing, tiles and fittings, society permissions and the best time of year to do the work. Prices vary by brand, city, contractor and the condition of what is behind your tiles, so treat every number here as a starting point for your own quotes, not a rate card.
How the numbers in this guide were built
- Materials: manufacturers’ own published prices, checked in November 2026: Hindware’s website for sanitaryware and diverters, Havells for water heaters, Dr. Fixit (Pidilite) for waterproofing products, and Orientbell’s May 2026 tile price guide for indicative branded tile prices.
- Labour and package rates: published cost guides from established interior and paint companies (Livspace’s 2026 bathroom renovation guide and Asian Paints’ waterproofing cost guide). These are national figures; NCR rates are often at the upper half.
- The sample bathroom: a common builder bathroom of about 5 ft x 8 ft (40 sq ft floor) with a 7 ft wall tile height, giving roughly 205 sq ft of floor and wall tiling, or about 225 sq ft after allowing 10 percent wastage.
GST at 18 percent applies to most contractor services and to many branded products. Online manufacturer prices are often maximum retail prices, and dealers in NCR commonly offer discounts on them, so your actual material bill may be lower.
Three scopes and what they typically cost
| Scope | What it includes | Typical range for a 40 sq ft bathroom |
|---|---|---|
| Refresh (no breaking) | New taps, shower, health faucet, WC seat, mirror and accessories; re-grouting; silicone sealing; exhaust fan; ceiling paint | Rs 25,000 to Rs 70,000 |
| Standard renovation | Remove old tiles and floor bed, replace concealed supply pipes, new waterproofing, new floor and wall tiles, mid-range sanitaryware and CP fittings, electrical points | Rs 1.2 lakh to Rs 2.5 lakh |
| Premium remodel | All of the above plus wall-hung WC with concealed cistern, large-format or designer tiles, glass shower partition, vanity unit, thermostatic or multi-outlet diverter, false ceiling, better lighting | Rs 2.5 lakh to Rs 5 lakh or more |
These are our working ranges built from the component costs below. They match the broad picture in published guides: Livspace’s 2026 guide, for example, puts a small bathroom from about Rs 1.25 lakh to Rs 2 lakh before tiles and fixtures. Larger master bathrooms, bathtubs, imported fittings and structural repairs push the total well above these bands.
Component costs and their basis
1. Demolition and debris
Breaking wall and floor tiles, removing the old screed and carrying debris down takes two or three days. Contractors usually price it as a lump sum within the job. Ask how debris will be bagged and removed, because most societies charge or fine for debris left in lobbies, and lifts must usually be booked and protected.
2. Plumbing
Livspace’s published estimate for bathroom plumbing starts at around Rs 28,000 per bathroom plus GST, excluding bathtubs and rain showers. That typically covers replacing hot and cold concealed lines, the diverter body, floor trap and connections. In older NCR societies, it is worth replacing galvanised iron or poor-quality concealed pipes completely once the wall is open; doing it later means breaking new tiles.
- Use CPVC or PPR pipes rated for hot water for the supply lines, with as few joints inside the wall as possible.
- Insist on a pressure test of the new lines before any wall is closed, and take photos of the pipe layout for future reference.
- Check the slope of the floor towards the drain and the condition of the floor trap; most “ceiling leaks” in the flat below come from the trap and the floor bed.
3. Waterproofing
Asian Paints’ guide puts bathroom waterproofing at roughly Rs 40 to Rs 120 per sq ft, depending on whether tiles must be removed, how severe the leakage is and how many layers are applied. Livspace lists bathroom waterproofing from about Rs 12,000 per bathroom plus GST.
To see what the material itself costs, take Dr. Fixit Bathseal Select, a liquid-applied membrane for wet areas under tiles. Pidilite lists it at Rs 1,800 for 4 litres and Rs 4,300 for 10 litres, with coverage of about 1.1 to 1.2 litres per sq m for two coats. Waterproofing the 40 sq ft floor, a 1 ft upturn around the walls and two 4 ft wide shower walls to 6 ft height comes to about 10.6 sq m, needing roughly 12 to 13 litres, or around Rs 6,000 of material at list price. Pidilite’s Pidifin 2K cementitious coating is another option, listed at Rs 580 for 3 kg and Rs 2,360 for 15 kg. Labour, surface preparation, a protective screed and the ponding test make up the rest of the cost.
- Waterproof the whole floor, take it up the walls by at least 300 mm, and higher (to around shower height) in the wet zone.
- Treat pipe penetrations and the floor trap junction with the manufacturer’s recommended sealant or tape.
- Do a ponding test: fill the floor with water for 24 to 48 hours and check the ceiling of the flat below before tiling.
Our separate guide on terrace and bathroom waterproofing before the monsoon goes into membranes and testing in more detail.
4. Tiles and laying
Orientbell’s May 2026 price guide gives these indicative ex-GST, ex-showroom prices for branded tiles:
| Tile | Size | Indicative price per sq ft |
|---|---|---|
| Ceramic wall tile | 300 x 450 mm | Rs 20 to Rs 50 |
| Ceramic floor tile | 300 x 300 mm | Rs 25 to Rs 45 |
| Anti-skid bathroom floor tile | 300 x 600 mm | Rs 35 to Rs 65 |
| Glazed vitrified (GVT) | 600 x 600 mm | Rs 40 to Rs 75 |
| Large-format GVT or PGVT | 800 x 1600 mm | Rs 80 to Rs 140 |
The same guide puts skilled tiling labour at about Rs 20 to Rs 35 per sq ft and tile adhesive at Rs 10 to Rs 15 per sq ft. Interior firms that quote a bundled installation rate (Livspace lists Rs 100 to Rs 200 per sq ft depending on tier) include adhesive, grout, supervision and their margin.
For our 225 sq ft sample, that means:
- Tiles: about Rs 7,000 to Rs 15,000 for basic ceramic, Rs 10,000 to Rs 17,000 for mid-range GVT and anti-skid floor, and Rs 25,000 or more for large-format or designer tiles.
- Labour and adhesive: about Rs 7,000 to Rs 11,000 at the per-sq-ft rates above; more for large slabs, which need levelling systems and more careful handling.
- Epoxy grout: worth the extra cost in shower areas because it resists stains and water better than cement grout.
Use a matt or textured anti-skid tile on the floor, and keep the floor tile size small enough to form a proper slope to the drain.
5. Sanitaryware and fittings
Prices below are from Hindware’s website (inclusive of taxes) in November 2026 and are a reasonable guide to the mid-market. Other major brands sit in similar bands, with premium lines much higher.
| Item | Example listed price |
|---|---|
| Wall-mounted WC (Ace) | Rs 8,990 |
| Wall-mounted WC, other models | Roughly Rs 10,500 to Rs 22,360 |
| Concealed cistern with half frame and drain set | Rs 10,190 |
| Concealed cistern with full frame and drain set | Rs 12,550 |
| Single-lever high-flow concealed diverter body | Rs 4,250 |
| Diverter trim set (exposed part) | Rs 1,500 to Rs 3,600 |
| 15-litre storage water heater (Havells, listed selling prices) | About Rs 10,300 (Valerio, MRP Rs 16,790) to Rs 17,800 (Magnatron Prime) |
A full set for one bathroom (WC with cistern, wash basin with mixer, diverter with overhead and hand shower, health faucet, angle valves, water heater, accessories) typically lands between Rs 35,000 and Rs 80,000 in the mid-market, and far more for designer collections.
6. Electrical, ventilation and ceiling
- Livspace estimates Rs 1,000 to Rs 2,000 per electrical point. A bathroom needs points for the geyser (on its own MCB), exhaust fan, mirror light and possibly a shaver socket away from the shower.
- An exhaust fan that vents outside, not into the shaft without a duct, prevents mould.
- A moisture-resistant false ceiling (PVC or cement board) hides pipes but must have an access panel for the cistern, geyser connections and the drain line of the flat above.
7. Vanity, mirror and glass partition
Livspace lists a basic 2 ft x 2 ft laminated vanity from about Rs 18,000. Toughened glass shower partitions vary widely with size, glass thickness and hardware; get two quotes and insist on toughened glass of the specified thickness with the stamp visible.
Worked estimate: standard renovation of a 40 sq ft bathroom
| Item | Low | High |
|---|---|---|
| Demolition and debris removal | Rs 8,000 | Rs 15,000 |
| Plumbing (new concealed lines, trap, pressure test) | Rs 25,000 | Rs 40,000 |
| Waterproofing (material, labour, screed, ponding test) | Rs 12,000 | Rs 25,000 |
| Tiles (about 225 sq ft) | Rs 10,000 | Rs 20,000 |
| Tiling labour, adhesive and grout | Rs 9,000 | Rs 18,000 |
| Sanitaryware, CP fittings and water heater | Rs 35,000 | Rs 70,000 |
| Electrical points and exhaust | Rs 5,000 | Rs 10,000 |
| Ceiling, mirror and accessories | Rs 6,000 | Rs 15,000 |
| Total before GST on services | About Rs 1.1 lakh | About Rs 2.1 lakh |
This is an illustration, not a quote. Add GST where your contractor charges it, and a contingency of 10 to 15 percent for surprises behind the tiles, such as a cracked drain line or a hollow floor bed.
Noida vs Gurugram: what changes
- Labour: rates in both cities are at the higher end of national guides. Premium sectors and gated societies with strict entry rules tend to see higher quotes because of limited working hours and lift access.
- Water quality: hard water is common in many Gurugram and Noida societies. Budget for a whole-bathroom softener or at least a filter on the geyser inlet, and prefer fittings with easy-to-clean aerators. Our guide on hard water solutions covers options.
- Society rules: both cities’ societies usually require an application to the facility manager or , a refundable security deposit and fixed working hours. Gated high-rises in Gurugram often also require labour registration and police verification of workers.
Society NOC and permissions
A bathroom renovation inside your flat normally does not need a building plan approval from the authority, but it does need your society’s permission. Our guide on renovating a society flat covers NOCs and rules in detail. For a bathroom specifically:
- Apply in writing with the scope, contractor details, expected dates and number of workers.
- Do not move the soil stack, cut structural walls or columns, or shift the WC to a position the vertical drain was not designed for.
- Inform the owner of the flat below, inspect their ceiling before work starts, and share the ponding test date.
- Follow the society’s rules on debris, lift protection and noisy work hours, typically weekdays within a set daytime window.
- Keep the deposit receipt and completion acknowledgement for future resale.
When to renovate in NCR
- Best window: roughly February to April, and late September to October. Waterproofing and screeds cure reliably, and there is time to spot problems before the monsoon.
- Avoid peak monsoon (July and August) if you can, because damp walls and humid air slow curing and mask leaks.
- Watch the pollution season: from late October to January, the Commission for Air Quality Management can invoke Stage III or IV of the Graded Response Action Plan, which restricts non-essential construction and demolition across NCR. In past Stage III orders, non-polluting interior work such as plumbing, carpentry, electrical work and interior decoration was allowed to continue, but dust-making work such as breaking, cutting and grinding can be halted. CAQM revised the GRAP schedule again in September 2026, so check the current order and your society’s notice before you plan demolition in winter.
- Timeline: a standard renovation of one bathroom usually takes two to three weeks, including curing time and the ponding test. Plan for a second bathroom or a temporary arrangement if you have only one.
Checklist before you sign a contractor
- An itemised quote that separates materials, labour and GST, with brands and model numbers for fittings and the tile series.
- The waterproofing product, number of coats, upturn height and a written ponding test.
- A pressure test for plumbing before walls are closed.
- A workmanship guarantee for leakage, ideally at least one to two years, in writing.
- A payment schedule tied to stages, with the last part due after the ponding test and final inspection.
- Responsibility for debris, damage to common areas and the society deposit.
As of November 2026: prices quoted are manufacturers’ published prices and published cost guides checked in November 2026. They vary by brand, dealer, city and site conditions, and change often. Use them to sense-check quotes, and confirm current GRAP restrictions and your society’s rules before work starts.
Frequently asked questions
How much does a full bathroom renovation cost in Noida or Gurugram?
For a typical 5 ft x 8 ft bathroom, a standard renovation with new plumbing, waterproofing, tiles and mid-range fittings usually costs about Rs 1.2 lakh to Rs 2.5 lakh. A refresh without breaking tiles can cost Rs 25,000 to Rs 70,000, and premium remodels go beyond Rs 2.5 lakh. Prices vary by brand and site conditions.
What does bathroom waterproofing cost?
Published guides put it at roughly Rs 40 to Rs 120 per sq ft, or from about Rs 12,000 per bathroom. Material for a small bathroom using a branded liquid membrane costs around Rs 6,000 at list price; labour, preparation and testing make up the rest.
Do I need permission from my society to renovate a bathroom?
Yes, most societies require a written application, a refundable deposit and adherence to working hours and debris rules. You should not alter the soil stack, structural walls or the WC position beyond what the drainage allows, and you should inform the flat below.
Can I renovate a bathroom during GRAP restrictions in winter?
Under past Stage III orders, non-polluting interior work such as plumbing, carpentry and electrical work was allowed, but dust-generating demolition, cutting and grinding can be stopped. Check the current CAQM order and your society's notice before planning a winter renovation.
Is a wall-hung WC worth the extra cost?
It makes floor cleaning easier and looks neater, but it needs a concealed cistern and frame (about Rs 10,000 to Rs 12,500 at Hindware's listed prices) and a strong wall. Make sure the cistern has an access plate and that your contractor has installed one before.
How long does a bathroom renovation take?
Usually two to three weeks for one bathroom, including curing and a 24 to 48 hour ponding test before tiling. Society working-hour limits and material delays can add time.
Sources
- Hindware: Ace wall mount toilet (listed price)
- Hindware: Concealo Neo cistern, half frame and drain set (listed price)
- Dr. Fixit (Pidilite): Bathseal Select product page
- Dr. Fixit (Pidilite): Pidifin 2K product page
- Orientbell: Tile price per sq ft in India (May 2026)
- Livspace: Bathroom renovation cost 2026
- Asian Paints: Waterproofing cost in India
- Havells: Valerio 15 L storage water heater (listed price)
- All India Radio News: CAQM approves revised GRAP schedule (September 2026)
- ThePrint (PTI): GRAP Stage III curbs, non-polluting interior work allowed (January 2023)
Updated 19 November 2026. This article is general information, not legal or financial advice; check current rules and project details before you decide.