Haryana clears Rs 1,662 crore civil works package for Gurugram Metro Phase 2 to Cyber City

Watercolour illustration of night metro construction among glass office buildings
Contents

What was approved

On 1 October 2026 the Haryana government cleared a civil construction package worth about Rs 1,662 crore for Phase 2 of the Gurugram Metro (the Millennium City Centre-Cyber City line being built by Gurugram Metro Rail Limited). Phase 2 is a 15.3 km elevated stretch with 14 stations running from Sector 9 through old Gurugram to DLF Cyber City. The tender was expected to be floated soon after the approval.

Where the line stands

  • Phase 1 (Millennium City Centre to Sector 9, about 15 km): the first pile was cast in Sector 45 in February 2026, and piling and pier work are progressing along the Southern Peripheral and Sector Road alignment.
  • Phase 2 (Sector 9 to Cyber City): utility shifting was ordered in mid-2026; civil works will follow the tender award.
  • Interchanges planned: Millennium City Centre (Delhi Metro Yellow Line), Subhash Chowk, Hero Honda Chowk, Sector 5 and DLF Cyber City (Rapid Metro), with a future link to the Namo Bharat corridor.

Reports differ on target dates; some put Phase 1 completion in 2027 and others in 2028.

What it means for property prices

The new line is the first mass-transit route through the southern sectors of Gurugram and old Gurugram, areas that have depended on roads. Areas likely to see the most interest include:

  • Sectors 45-57 and Sohna Road around Subhash Chowk.
  • Old Gurugram colonies around Sector 4, 5, 9 and 10, where builder floors and plotted homes dominate.
  • Palam Vihar and Sector 22-23 near the Cyber City end.

Metro-led price gains usually happen in steps – at approval, at visible construction and at opening. Old Gurugram has already seen some anticipation, so buyers should not assume all the upside is still ahead.

What to check

  • The actual station location and distance from the property on GMRL’s alignment plan – a “near metro” label can mean 2 km.
  • Construction-phase disruption on your access road over the next two to three years.
  • For builder floors in old Gurugram, the building plan approval and occupation certificate for each floor.

Buyers should also note that the Phase 2 cost estimate and timelines may change once bids are received; a World Bank-linked financing review has been part of the process, and reports have put the total Phase 2 cost far above the civil package alone.

Sources

News summarised by ADiHomes from the sources above. Check the RERA record and the builder's documents before you pay.

Share WhatsApp Copy link

More news

Back to top

Own a property in Delhi NCR? Post it free.

Owners can list up to 2 properties and agents up to 5, at no cost. Every listing is checked before it goes live.

Post property free Browse projects